Tuesday, 23 May 2017

TBM Rachna Crosses River, Touches Kolkata , Moves on to Shaft

Extremely Sorry for my late call !

Afcons-Transtonnelstroy JV's TBM S639 Rachna has successfully completed boring the 1st ever tunnel section under a river in the Indian Subcontinent !

Congratulating the Afcons team for their beautiful work . 500 metres of tunneling has been completed within 36 days ! Now that's Verryyyy Faast !



Well as of now , the TBM has not entered the city yet . It has just touched the city riverbank and will now continue to bore the tunnel upto the Evacuation Shaft located 100 metres away from Riverbed .



Now , it's quite demotivating and unfortunate to hear that the TBMs will be parked year for 'x' number of days , where that value of x is unknown .

Tunnel under River ! Clicked by Sanjoy Chattopadhyaya









Total of 25 buildings that may fall down during boring of tunnel along the Brabourne road need to be evacuated and kept undisturbed and structurally supported with extra materials for at least 10 to 15 days ! KMRC has promised to repair the damaged which will occur to them .

The Mahakaran station will be located near 3 heritage buildings of very poor condition. Now , Afcons cannot construct the station until and unless the National Monuments act gets amended to allow excavation of shaft within 100 metres of those 3 heritage buildings .

 Now , High court is eager to clear the junks from this mighty project ! Here's a quote from a news portal which I came across ....


High court takes first step to vacate crumbling Brabourne Road buildings
KOLKATA: Calcutta high court has directed Transtonnelstroy Afcons to serve a legal notice to owners and occupants of 25 'critical buildings' on Brabourne Road, asking them to take necessary steps to temporarily evacuate or suspend business so that the buildings can be revamped before the tunnel boring machine starts boring underneath. Afcons is constructing the tunnel from Howrah Maidan to Mahakaran. The occupants have been asked to appear before the court on June 6. 

In the order, Justice Dipankar Dutta has directed Afcons to "implead the owners of the buildings as respondents in the writ petition and take necessary steps that would meet the needs of all parties".

Sources in Kolkata Metro Rail Corporation (KMRC), the implementing agency of the Rs 8,900-crore project, said the notices were mainly aimed at the nine buildings that are in "very poor condition". Residents of other buildings may not have to shift at all. 

The notice has already been pasted on some properties and the rest have been handed over to individuals staying or working at these buildings. "Since the legal owners/occupiers for the buildings could not be identified, the notice has been pasted on the wall to draw the attention of the legal owners/occupiers so that they may take necessary steps," the notice has explained.


The order is sacrosanct and irreversible, KMRC officials said, since they are not from agencies like KMC, which is not used to working under such short deadlines, or from the state government, which is often bogged down with red tape, nor from a construction company, which can be challenged in court. Since the order has come straight from the court, it makes "the action very clear for the state government representatives, KMC and the state advocate general."

According to KMRC officials, the TBM, which is likely to reach the eastern shore soon and would cross Strand Road to head towards Brabourne Road thereafter, has been slowed as per court's instructions. "But the machine will suffer damages if stopped completely. Hence, the immediacy," an official said.


The residents, shop-owners of the buildings will have to stay away from the properties for a short while — about 10 or 15 days, or even less — KMRC sources said. By this time, damages in the buildings will be repaired and the required strengthening done. "The east-bound TBM will move only after the crumbling buildings are taken care of," said an official.

On 22nd April 2017 , TBM Prerna was finally pushed towards the Riverbed after a resting period of two and half months . I already mentioned that Prerna had a breakdown while boring tunnel in between Howrah Maidan and Howrah Station .

Prerna is scheduled to enter Riverbed tomorrow , on 23rd of May , 2017 . Hope , Afcons makes it as easily as it made the previous one !

Stay tuned for more Kolkata Metro Updates. Don't forget to share my posts because it really motivates me to write more and more posts to encourage you and make you aware of Mass Rapid Transits . Sorry again for the delay in writing the post . Have a nice day ! Bye bye !

-------- MetroRail Blog

3 comments:

  1. pls carry on boss. grt job done for update story of kolkata metrorail. pls update of garia to airport metro news.

    ReplyDelete
  2. Love your blogs. Late to your blog, but its been a great find. Hope to get some more brilliant stuffs from you!!

    ReplyDelete