Finally ! After suffering for 5 years , the 365 metres Duttabad Stretch of the Upcoming 16 Km East West Metro or Kolkata Metro Line 2 is nearing completion !
Duttabad is a slum area beside E.M. Bypass . The East-West corridor of Kolkata Metro will be passing through this area . Just after construction started , this 365 m section faced a huge encroachment problem , which stalled the project for 5 Years . After repeated Political Interventions in this Engineering Marvel , the stretch finally got encroacher-free .
Here's a video which you may like . This video shows the entire stretch of Duttabad . The videographer risked himself while capturing the video , as the site was full of Securities . Check this out :-
Click Here to Watch Video
Check out these images of City Centre Metro Station :-
It is being expected that Viaduct installation work will be complete by April end . Tracks will be then laid within another couple of weeks . Laying of tracks is already complete throughout the entire elevated stretch . For More Updates of Kolkata Metro , view Kolkata Metro Section .
----- MetroRail Blog
Follow MRB on Facebook
Follow MRB on Twitter
Email Me
Duttabad is a slum area beside E.M. Bypass . The East-West corridor of Kolkata Metro will be passing through this area . Just after construction started , this 365 m section faced a huge encroachment problem , which stalled the project for 5 Years . After repeated Political Interventions in this Engineering Marvel , the stretch finally got encroacher-free .
All piers are completely erected . This stretch will be having Galvanized Steel precast Girders , which requires lesser installation time than Concrete Girders . MetroRail Blog is the first one to publish this news . Check out these photos captured by one of my source in Kolkata Metrorail Corporation Limited :-
New Viaduct at Duttabad
New Girder
Stainless Steel Girder being placed on top of Pillars at Duttabad
The Duttabad Curve
Entrance to Duttabad Site
Here's a video which you may like . This video shows the entire stretch of Duttabad . The videographer risked himself while capturing the video , as the site was full of Securities . Check this out :-
Click Here to Watch Video
Check out these images of City Centre Metro Station :-
Beautiful KMRC Logo made on the
median of Road
Check Out these images of Central Park Depot :-
KMRCL Control Building
Depot Boundary
It is being expected that Viaduct installation work will be complete by April end . Tracks will be then laid within another couple of weeks . Laying of tracks is already complete throughout the entire elevated stretch . For More Updates of Kolkata Metro , view Kolkata Metro Section .