Sunday, 19 March 2017

Work resumes at Subhas Nagar for Airport Metro

Finally !! The Subhas Nagar Landlock finally broke and the building demolitions started .

The 800 m stretch were suffering from 573 encroachers . But now , metro has started demoloshing the buildings . Have a look at the photos :- 


Piling Work started inside Locality .

I also visited the entire stretch of Line 4 yesterday . Have a look at these pictures !!

Metro Ramp between 
Jessore Road and Airport

Ramp

Viaduct near Jessore Raod

Viaduct Near Jessore Rd


Viaduct

Line 4 Headquarter

Newly demolished Railway Track

Piling work going at Green Park

Pier Cap beside Canal near Noapara

Piers near Noapara

Metro Viaduct near Jessop Factory

If all goes well , metro may roll on the viaducts by December 2018 .

An Engineer confirmed that the tunnels in between Airport and Jessore road will be bored in Shield Tunneling Method (which is very time consuming process).😢

Following are the list of Major works which are left for Line 4 :-

1. Segment launching over Eastern Railway     Track at Dum Dum Cantonment

2. Tunneling in between Jessore Road and         Airport

3. Joining of Line 4 tracks with Noapara             Shunting Yard

4. Pier Erection at Subhas Nagar

5. Construction of Airport Metro Station             (interchange with Line 6)

NOW HERE IS A VERY IMPORTANT NEWS

I have Shifted My YouTube Videos to a New Channel ! My Earlier Channel Had Some Problems with Google . Thus , My Videos Were Shifted . Click Here To View New Channel . You can Watch This video to Find out more . I Am Shooting 5 Documentary Films For 5 Separate Lines which will include History , Present Condition and Future of Every Lines along with Graphical Representation . So Please Subscribe this Channel . Thank You .

For More Updates , Check our Social Networking Sites :-

FACEBOOK LinkedIn Twitter YouTube Email

No comments:

Post a Comment